In Progress Roads and Transport Engineering Department

Central Market Road Upgrade

Rehabilitate the main commercial corridor with safer sidewalks and traffic calming.

Current progress
68%
Budget
ILS 2,450,000
Location
Central Market Area

Project scope

The project covers resurfacing 1.8 km of roadway, new sidewalks, safer crossings, and efficient lighting around the central market.

Updates

2 updates

Sidewalk installation started

2026-05-10 68%

Sidewalk paving and accessible tactile elements have started.

Underground works completed

2026-03-18 48%

Stormwater drainage and underground utility works were completed in the northern section.